This summer at UCSF Parnassus Heights, construction for several major projects is continuing – and will go into full swing this fall. Work is underway to build a New Hospital at Parnassus Heights (NHPH), a new Parnassus Research and Academic Building (PRAB), and a new fuel tank facility. Improvements also are underway to the Health Sciences Instruction and Research (HSIR) east and west towers for exterior repairs, and seismic and life safety updates.
This quarterly story shares what you need to know about major construction impacts from these projects through summer 2023.
Dates and other project details are subject to change.
- You can find this story and other design and construction news on the UCSF Real Estate website. A fall update will be available in October 2023.
- Community updates on UCSF construction and design are available through UCSF Community and Government Relations (CGR). You can sign up for UCSF CGR updates for Parnassus Heights at www.ucsf.edu/cgr/signup and find the latest updates at www.ucsf.edu/cgr.
New Hospital at Parnassus Heights
To serve the city with world-class care for the next century, UCSF is constructing a 15-story hospital on the Parnassus Heights campus on the current Langley Porter Psychiatric Hospital (LPPH) site. Construction will continue through 2029, with the new hospital opening in 2030.
Beginning February 2022 through April 2027, 20 Site Make Ready (SMR) and 12 Hospital Make Ready (HMR) major projects are required to prepare for demolition of LPPHC and construction of the new hospital building at Parnassus Heights. We are communicating impacts of this work broadly to UCSF faculty, staff, learners, patients and visitors, and the community.
The new hospital is part of the Comprehensive Parnassus Heights Plan.
Construction Hours
8 a.m. to 5 p.m. Monday through Friday
Expected Project Completion Date
2030
Project Contact
[email protected] or 415-476-6577
Moving Patients at Langley Porter Psychiatric Hospital
Temporary Traffic Signal on Parnassus Avenue (Operational in Late August)
Other Work Underway for the New Hospital Project
What You Can Expect
Parnassus Research and Academic Building
A new state-of-the-art Parnassus Research and Academic Building (PRAB) is under construction on the Parnassus Heights campus. PRAB will be a new home for the School of Nursing, and have an expanded education space, and space for multiple health and science disciplines. The new building will encourage collaboration and support UCSF staying at the cutting edge of discovery, learning and care.
The building also will serve as temporary spaces for research and academic groups as the campus undergoes several major improvements for the Comprehensive Parnassus Heights Plan through 2030.
Construction Hours
- 7 a.m. to 5 p.m. Monday through Friday
- 8 a.m. to 5 p.m. for noisy work
Expected Project Completion Date
2027
Project Contact
Hard Demolition of UC Hall Starting in Early August
Other Work Underway for the Project
What You Can Expect
Health Sciences Instruction and Research (HSIR) Towers Improvement Program
Three major projects are part of the improvement program for the Health Sciences West (HSW) and Health Sciences East (HSE) towers. The updates will run concurrently while the towers remain occupied. They include exterior repairs, seismic improvements and life safety updates.
The HSIR complex is made up of two, 16-floor towers with an elevator and corridor that connects the towers. About 90% of the building includes labs and research space.
Currently, some scaffolding and shrink wrap are currently on sections of the towers for construction. In April, workers started adding shrink wrap to the south- and east sides of the HSW tower, which is expected to remain through spring 2024.
Construction for the project is nearly 25% complete and is expected to reach 50% completion by early 2024.
Construction Hours
- 7 a.m. – 5 p.m. Monday through Friday for interior and exterior work
- 10 p.m. – 6 a.m. Monday through Friday for interior fire sprinkler work
Expected Project Completion Date
- Late 2024 for life safety and seismic projects
- Early 2025 for exterior repairs
Project Contact
350 Scheduled Shutdowns for Construction
Phase 2: Shrink-Wrap Installation Starting on HSW and HSE Towers
Other Work Underway for the Project
What You Can Expect
Other Construction Projects at Parnassus Heights
PCUP Fuel Tanks Replacement
Two Water Projects at Parnassus Heights